Building New Outdoors Stairwell

Early September, 2019














old steps removed

extra soil removed

to accommodate

the much wider stairs

first pour of concrete

rebuilding the foundation

building the outer forms

for vertical walls

adding re-bar for

strengthening concrete walls

adding more reinforcing bar

forms now ready for the

final pour of concrete

refurbished steel stairs

no more wooden steps

concrete pour complete

forms remain for a few days

forms removed after two days



slots on near end wall

are top support for stairs

slowly add some fill

about a foot each day

Prepared for winter

Landscaping scheduled

for spring of 2020

Steps in position.

The extra top step

soon to be removed

Section of railing

protecting the opening

Top step now level